← HomePower Infrastructure
Direct adjacency to a Transelectrica substation inaugurated in May 2026
The Transelectrica 400/220/110 kV substation adjacent to this site was commissioned in May 2026. The kV figures are its voltage levels; the MVA figure is the transformer power installed at the substation.
450 MVATransformers installed at the substation; capacity for this project will be set by the grid study
400/220/110 kVVoltage levels at the substation
May 2026Substation commissioned
No ATR yetNo capacity allocated to the project
Transelectrica Substation — Operational now
Commissioned in May 2026 and operated by CNTEE Transelectrica SA, the Romanian transmission system operator. It is national grid infrastructure adjacent to this site, separate from the land process.
Grid Connection — Next step
A grid-connection study offer is in hand. Capacity for this project will be set by the grid study, followed by the ATR. No ATR yet, and no capacity allocated to the project.

Utilities Under Way
Grid, fibre and water: what is moving now.
A grid-connection study offer is in hand. Orange Business has started a fibre-connection survey; fibre is about 500 m away. The Mayor has offered to bring water to the parcel for an investor.
No ATR yet, and no capacity allocated to the project. Full documentation (council resolutions, grid correspondence, technical studies, site survey) is available to qualified parties under NDA. Request access: investors@resitadata.com
The Mayor has offered to bring water to the parcel for an investor.

That's the real state of it. If it fits, talk to us.
No ATR yet, and no capacity allocated to the project. The land route (concession or purchase) is being finalised with the Municipality. A real site next to a live substation. If that's what you're looking for, get in touch. If it isn't, no hard feelings.
Full documentation (council resolutions, grid correspondence, technical studies, site survey) is available to qualified parties under NDA. Request access: investors@resitadata.com