A real site next to a live substation.
The facts below are summarised on this website; the documents behind them are in the data room, available under NDA.
- Adjacent Transelectrica 400/220/110 kV substation, commissioned in May 2026
- 450 MVA of transformers installed at the substation; capacity for this project will be set by the grid study
- First stage of about 3 ha (30,000 m²); expansion potential toward 31 ha, not secured
- Strategic partnership with the Municipality, a joint technical working group and a letter of support from the Mayor
- Parcel moved into the municipality’s private domain by the Council (June 2026)
- Utilities under way: fibre survey by Orange Business, grid-connection study offer in hand, water offered by the Mayor
