Sale of 80 to 90% of the project company, to a partner who takes the site forward.

Resita Data Infrastructure SRL is the project company for an early-stage data centre site in Reșița, western Romania, adjacent to a Transelectrica 400/220/110 kV substation commissioned in May 2026. The partner takes the site through land, grid connection and development; the founder stays as minority shareholder and local operating partner.

There are 450 MVA of transformers installed at the substation; capacity for this project will be set by the grid study. No ATR yet, and no capacity allocated to the project. The first stage is about 3 ha (30,000 m²), with expansion potential toward 31 ha, not secured. The land route (concession or purchase) is being finalised with the Municipality.

Full documentation (council resolutions, grid correspondence, technical studies, site survey) is available to qualified parties under NDA. Request access: investors@resitadata.com

80–90%

Of the project company offered for sale

To a partner who takes the site through land, grid connection and development. The founder stays as minority shareholder and local operating partner.Resita Data Infrastructure SRL · CUI 54450187
450 MVA

Transformers installed at the adjacent substation

Transelectrica 400/220/110 kV substation, commissioned in May 2026. Capacity for this project will be set by the grid study; no ATR yet.kV: voltage levels · MVA: transformer power
~3 ha

First stage, on municipal land

30,000 m², with expansion potential toward 31 ha, not secured. The Council has moved the parcel into the municipality’s private domain (June 2026).Land route: concession or purchase, being finalised
Institutional Entry

An early-stage position, not a finished asset.

Resita Data Infrastructure SRL holds the municipal partnership and the land and grid processes described on this site, nothing more and nothing less. 80 to 90% of the company is offered to one partner, introduced directly or through a broker or adviser. Intermediary fees are paid only on success, by the buyer; no retainer, no upfront payments.

The Site · What Is in Place

A real site next to a live substation.

The facts below are summarised on this website; the documents behind them are in the data room, available under NDA.

  • Adjacent Transelectrica 400/220/110 kV substation, commissioned in May 2026
  • 450 MVA of transformers installed at the substation; capacity for this project will be set by the grid study
  • First stage of about 3 ha (30,000 m²); expansion potential toward 31 ha, not secured
  • Strategic partnership with the Municipality, a joint technical working group and a letter of support from the Mayor
  • Parcel moved into the municipality’s private domain by the Council (June 2026)
  • Utilities under way: fibre survey by Orange Business, grid-connection study offer in hand, water offered by the Mayor
The Terms · How the Sale Works

One partner takes the site forward.

The partner takes the site through land, grid connection and development. No ATR yet, and no capacity allocated to the project.

  • Sale of 80 to 90% of the project company
  • The partner leads land, grid connection and development
  • The founder stays as minority shareholder and local operating partner
  • Intermediary fees only on success, paid by the buyer
  • No retainer, no upfront payments
  • Full documentation in the data room, after a mutual NDA
What the acquiring partner gets
The project company (Resita Data Infrastructure SRL)
  • 80 to 90% of the SRL (CUI 54450187)
  • The municipal partnership and support described on this site
  • The land route (concession or purchase), being finalised with the Municipality
  • The grid-connection process: study offer in hand, ATR to follow
  • The full documentation, in the data room
Partner’s role
  • Complete the land route with the Municipality
  • Grid study and ATR, which set the capacity (cost and timeline partner-borne)
  • Engineering, design, permits and construction
  • Tenants and commercial pipeline
  • Working with the founder as minority shareholder and local operating partner

Sale of 80 to 90%

— the transaction

The buyer acquires 80 to 90% of Resita Data Infrastructure SRL and takes the site through land, grid connection and development. Terms are agreed in negotiation, after due diligence under NDA.

Founder stays on

— after the sale

The founder keeps a minority stake and stays as local operating partner.

Intermediaries

— fees on success only

Brokers and advisers who introduce the buyer are paid only on success, by the buyer. No retainer, no upfront payments.

Development Roadmap

Milestone-gated.

Each phase gates the next. Phase 01 is in place, and the partner process (Phase 02) is open now.

Phase 01

Site Origination

Strategic partnership with the Municipality, a joint technical working group and a letter of support from the Mayor; parcel moved into the municipality’s private domain (June 2026); project company incorporated.

~3 ha first stageIn place
Phase 02

Partner Entry & Due Diligence

Mutual NDA, data room and due diligence, leading to the sale of 80 to 90% of the project company. Interested parties are welcome to start a conversation now: see Contact.

Documents under NDAActive — now
Phase 03

Land & Grid Connection

The land route (concession or purchase) is completed with the Municipality. The grid study sets the capacity for the project, followed by the ATR.

Capacity set by the grid studyPartner-led
Phase 04

Campus Development (indicative)

Engineering, permits and construction, led by the partner, with phased build-out subject to the grid study and the ATR.

Toward 31 ha · not securedIndicative
What Is in Place

What follows is what we can actually back up.

Short and current. The documents behind each item are available to qualified parties under NDA.

Transelectrica substation

400/220/110 kV, commissioned in May 2026, adjacent to the site. 450 MVA of transformers installed at the substation; capacity for this project will be set by the grid study.

CNTEE Transelectrica SA

Grid connection

A grid-connection study offer is in hand. No ATR yet, and no capacity allocated to the project.

Grid-connection study offer

Municipal support

A strategic partnership with the Municipality, a joint technical working group and a letter of support from the Mayor. The Council has moved the parcel into the municipality’s private domain (June 2026).

Municipality of Reșița

Land route

The land route (concession or purchase) is being finalised with the Municipality. First stage of about 3 ha (30,000 m²); expansion potential toward 31 ha, not secured.

Municipality of Reșița

Fibre

Orange Business has started a fibre-connection survey; fibre is about 500 m away.

Orange Business

Water

The Mayor has offered to bring water to the parcel for an investor.

Municipality of Reșița

That's the real state of it. If it fits, talk to us.

No ATR yet, and no capacity allocated to the project. The land route (concession or purchase) is being finalised with the Municipality. A real site next to a live substation. If that's what you're looking for, get in touch. If it isn't, no hard feelings.

Full documentation (council resolutions, grid correspondence, technical studies, site survey) is available to qualified parties under NDA. Request access: investors@resitadata.com